In the change control process, after a change request is submitted, what is the next step?

Disable ads (and more) with a membership for a one time $4.99 payment

Master UCF's Project Management exam with our comprehensive study tool. Dive into flashcards, multiple choice questions, and detailed explanations to ace your upcoming test. Prepare for success!

In the change control process, once a change request is submitted, the next step is integrated change control. This phase involves a systematic approach to managing changes across the entire project. Integrated change control ensures that all changes are evaluated, approved or rejected, and documented accordingly, which is crucial for maintaining project alignment with its objectives and preventing scope creep.

During integrated change control, the project manager and project team assess the implications of the change on various aspects of the project, including scope, timelines, costs, and resources. This assessment is vital to understand how the change will affect the overall project and to facilitate informed decision-making regarding approval.

The importance of integrated change control lies in its role in maintaining project integrity and ensuring that changes are made thoughtfully, with consideration of their impact on project success. By following this step, project teams can strategically manage adjustments and sustain progress towards project objectives.